(a) The moving roof weighs 1,000 tonnes and covers 5,200 square metres. The folding fabric concertina design is in two sections. The fabric is strong, flexible and translucent to help provide light and an airy feel. The height of the roof from the ground is 16 metres.
(b) The roof has been designed to maintain pre-existing levels of light and air to the court when the roof is open, and when closed, an air management system removes condensation from within the bowl to provide good court surface conditions conducive to the playing of tennis.
(c) The roof will take 8–10 minutes to close. Once closed, and depending on prevailing weather conditions, the humidity control air system will require further time to create the optimum conditions for play to be resumed as quickly as possible. Because of the time taken to close the roof, the Centre Court covers will be deployed as soon as it starts to rain.
(d) The roof is fitted with sports LED lights (required by high-definition television), which are turned on manually once the roof has fully closed. The LED lamps will light up instantly, and therefore there is no waiting time for the lights to warm up to the sports playing and broadcast light level.
(e) For the roof to be opened the LED sports lights require minimal cool down time, and therefore the roof can be opened immediately after the lights are turned off. It will take 8–10 minutes to open the roof and for the court to be ready for play.
(f) The roof can safely be deployed in wind conditions of up to 43 mph (69 kph).
(g) Planning constraints require play to finish at 11.00pm. The referee will decide the most appropriate time to stop play in the same way as he does for fading light.
These basic principles will govern the use of the roof:
(a) The Championships is an outdoor daytime event. Therefore, in good weather, the roof will only be used if it is too dark to play on without it.
(b) The Referee has ultimate control over use of the roof and his decision is final.
(c) Timings of scheduled play on Centre Court in 2018 are intended to be on the same basis as 2017. This includes the number of matches and the likely timing of those matches to be put on the court. There can be many different circumstances which will govern the opening and the closing of the roof, hence the ultimate control of the Referee. That said, the following may be useful guidelines:
Best efforts will be made to start play each day with the roof open. However, 45 minutes before the start of each day’s play, the Referee will decide if the first match will start with the roof open or closed.
If a match is suspended due to rain, the normal covers will first be deployed, before the roof is closed, and the match continued. Due to the change in playing conditions, players will get a full warm-up on returning to court. If the projected interruption is sufficiently brief, as determined by the Referee, the normal covers will be used and play then continued with the roof open.
The Referee will decide to open or close the roof before the start of each subsequent match
Any match originally scheduled for Centre Court will normally be completed if possible and if necessary the roof closed for reasons of rain or light. Any matches added to the original schedule may be stopped without the deployment of the roof at the discretion of the Referee.